AS OF NOVEMBER 1, 2017

CONSTRUCTION ACTIVITY 

 

  • Equipment consists of three graders, 5 packers, one water truck, one excavator, 10 clam-dumps, and three bulldozers

  • Final road grading

  • Demobilization of all camps and equipment

  • Installation of guardrail and regulatory traffic signs underway 

CULVERTS & BRIDGES 
 

  • All culverts have been installed

  • Repair work was carried out at two culverts (KM 74 and KM 87)

PIT ACTIVITY 
 

  • Reclamation complete at Pit 177, Pit I401A, Pit GSC4, and Pit PW10

  • Final reclamation in progress at Pit 174

  • Maintenance of ditches and trenches underway at Pit 312, as well as repair of pit access road and camp pad; two bulldozers working for crushing operations

  • Two bulldozers stockpiling at Pit 312

ENVIRONMENT
 

  • No spills or incidents to report

EMPLOYMENT
 

  • There are 70 people currently employed on the project, 58 of whom reside in the Northwest Territories (NWT)

  • A total of 139,602 employment days have been achieved to date of which 101,079 were for residents of the NWT